Step 01: Install nutplates to the VA-188 Flow Scan Mount Bracket per the call-outs in Figure 1 if using a Flo-Scan Fuel Flow Meter or Figure 2 if using a FT-60 Fuel Flow Meter.

Note: The fuel flow meter provided will be one of two types. Page 28-05, Figure 1 includes a depiction of both types. Determine the fuel flow meter provides with the kit and use the applicable hardware.
 
Step 02: Cleco the VA-188 Flow Scan Mount Bracket to the F-1272 Fwd Fuse Floor Skin. Final-Drill #30 the four attach holes. Remove the bracket and deburr both parts.  
Step 03: Rivet the VA-188 Flow Scan Mount Bracket to the F-1272 Fwd Fuse Floor Skin per call-outs in Figure 2.  
   
CENTER SECTION MID FUSE LOWER FUSE  SIDE SKINS ROLLOVER TAIL ATTCH  SEATS PEDALS FUEL FWD FUSE  BUILDERS LOG
Drill Chart Tap Chart Bolt Chart Nut Chart Rivet Chart Washer Chart Rod Ends Vendors Shop Home
 

Disclaimer : Information contained on this Site may be out of date and /or inaccurate - Please Confirm any important data with a reliable source.