Page  21.12 Mid Fuse Ribs & Bottom Skins     
21.01 21.02 21.03 21.04 21.05 21.06 21.07 21.08 21.09 21.10  
21.11 21.12 21.13 21.14 21.15 21.16 21.17 21.18 21.19 21.20  
Step 01: Separate the F-1203J Bulkhead Doubler by removing the hatched areas shown in Figure 1.  
Step 02: Rivet the 17 nutplates shown in Figure 2 to the F-1203 Bulkhead using the rivets called out. DO Not install a nutplate at either end of the top row of nutplates as indicated in the figure.  
Step 03: Rivet the F-1203J Bulkhead Doublers to the F-1203A Bulkhead using the rivets called out in Figure 2.  
   
VERTICAL STAB RUDDER ANTI-SERVO TAB  STABILATOR TAILCONE EMP ATTACH  EMP FAIRINGS  BUILDERS LOG

Note: This is my builders log and is not Intended to replace Vans Construction drawings