Page 32.12: FLIGHT
CONTROLS |
|
Step 01:
Set the Rudder Pedal Rigging Stop between the F-1290 Pedal Blocks and
the F-1202F Bulkhead as shown in Figure 1. |
|
Step 02: Draw a line
down the center of the top surface of the F-1258 Rudder Cable Links |
|
Step 03: Center the
rudder, pull the F-1239 Rudder Cables tight, center the line drawn on
the WD-1258 Rudder Horn, then clamp the rudder cable links to the Rudder
Horns as shown in Figure 2. |
|
Step 04: Make sure the
rudder is still centered, then mark the hole centers of the WD-1205
Rudder Horns on the F-1205 Rudder Cable Links. |
|
Step 05: Remove the
Rudder Pedal Rigging Stops. |
|
Step 06: Remove the
marked F-1258 Rudder Cable Links from the F-1239 Rudder Cables, then
secure the rudder cables to the WD-1205 Rudder Horn using the hardware
called out in Figure 3. |
|
Step 07: With a bolt
through the ends as shown in Figure 4, clamp a marked F-1258 Rudder
Cable Link to the top of an unmarked rudder cable link. |
|
Step 08: Drill #30
through both F-1258 Rudder Cable links at the marks, then final-drill #
12. |
|
Step 09: Repeat the
last two steps with the remaining marked add unmarked F-1258 Rudder
Cable Links. |
|
Step 10: Trim the
F-1258 Rudder Cable Links as shown in Figure 5. The rudder cable links
with the holes closer together are the F-1258 - R, those with the holes
farther apart are the F-1258-L. |
|
Page 32.12: FLIGHT